Project Description
Project Scope
Soletanche Bachy Canada delivered the installation of a new dock wall at the Port of Oshawa, supporting the relocation of industrial port activities and the modernization of the waterfront infrastructure.
Working in a marine environment, the project involved removing sections of the existing dock structure and constructing a new combi-wall system anchored with tie-backs and integrated into a reinforced concrete cap. The upgraded dock face now supports the docking of larger vessels and improved cargo handling operations.
Notably, SB Canada had previously contributed to the original dock wall installation decades earlier through Bermingham, reflecting the company’s long-standing history at the Port of Oshawa.
Solution
The new dock structure was constructed using a combi-wall system of alternating pipe piles and sheet piles, designed to retain waterfront soils and provide long-term stability for port operations.
Because of the length of the wall, precise pile alignment was critical to avoid cumulative installation errors. SB Canada developed a custom installation template to guide the placement of piles and ensure accuracy along the dock face.
Construction was carried out from marine equipment under challenging site conditions, including heavy armour stone removal, marine excavation, and tie-back installation from barges.


Project Outcome
The new dock wall at the Port of Oshawa provides upgraded marine infrastructure capable of supporting modern cargo operations and larger vessels.
Through the installation of a combi-wall system anchored with tie-backs, Soletanche Bachy Canada delivered a durable waterfront structure while maintaining safe execution and strong collaboration with the Port Authority. The project was completed on schedule and included value-engineered solutions that improved constructability and reduced costs.
Key takeaways
- Successful delivery of marine dock infrastructure in an active port environment
- Installation of a combi-wall system designed for long-term performance
- Precise pile installation to maintain alignment along the dock face
- Value engineering that improved constructability and project efficiency
Client Testimonial
“SB Canada completed the project on time and at all times were professional and innovative, even suggesting a money-saving alternative to the original design. The Oshawa Port Authority does not hesitate to recommend SB Canada in their future endeavours.”
– Ms. Donna Taylor
President & CEO, Harbourmaster



