CN Fountain Slide
About the Project: Build Fast Track Mitigation Project (June 2016 – November 2016)
Our Task: Installaltion of:
- 250 micropiles. Diameter = 346mm, lengths range = 24.4m – 30.5m
- 30 strand anchors. 18 strands per anchor. Length = 36m each
- Concrete waler at base of existing beam and lagging retaining wall
Techniques used: Micro Piles